Deshuttering period for formwork

  Element Description  Summer      Winter Vertical member of column,  wall,beam    16 hr      24 hr Soffit of slab       3 days      7 days Soffit of beam    7 days      10 days Props of slab-Span upto 4.5m     7 days      10 days Props of slab-Span greater than  4.5m    14 days      14 days Props of beam-Span upto 6 m    14 days      14 days Props of beam-Span greater than  6m    21 days      21 days