Deshuttering period for formwork

 

Element Description

 Summer

    Winter

Vertical member of column,

 wall,beam

   16 hr

    24 hr

Soffit of slab   

   3 days

    7 days

Soffit of beam

   7 days

    10 days

Props of slab-Span upto 4.5m 

   7 days

    10 days

Props of slab-Span greater than

 4.5m

   14 days

    14 days

Props of beam-Span upto 6 m

   14 days

    14 days

Props of beam-Span greater than 

6m

   21 days

    21 days

Comments